STONEPARK CRESCENT_CSO_ASHBURTON

Spill evidence · Friends of the Dart

STONEPARK CRESCENT_CSO_ASHBURTON

Combined sewer overflow · SBB01186 · feeds BUCKFASTLEIGH STW
Wet weather

The discharge

Spill day
Wednesday, 8 January 2025
Started
8 Jan 2025, 12:52
Ended
8 Jan 2025, 13:49
Duration
56 minutes 20 seconds
Receiving water
Ashburn
Parish
Ashburton

Rainfall evidence

Daily rainfall at the matched gauge (Austins Bridge) for the spill day and the days before. A spill is dry when every day in the window is ≤ 0.25 mm.

1-day window: Wet weather3-day window: Wet weather4-day window: Wet weather
DateRainfall
08/01/2025 (spill day)15.2 mmrain
07/01/20250.1 mmdry
06/01/20259.9 mmrain
05/01/202528.1 mmrain
04/01/202561.3 mmrain

River flow that day: 25.861 m³/s. Verify at the EA rainfall station.

Gauge proximity

Outlet (red) vs matched rain gauge (blue), 3.6 km apart. Closer means the rainfall reading is more representative of the overflow.

Loading map…

Severity & context

Bathing water
Not Applicable
Shellfish water
Not Applicable
Ahead of the works
No — the works was also overflowing that day.
EA annual return (2025)
39 counted spills · 175 h total
Monitor uptime (2025)
100% operational
Method & provenance. Dry/wet classification is decided by rainfall at the nearest EA gauge — ≤ 0.25 mm on the spill day and each preceding day of the window (how we classify). Spill data: Environment Agency EDM (outlet SBB01186). Rainfall: EA Hydrology gauge fd8ea26c-8052-48c5-a1bb-bbd5ebbbb3d3_364176. A dry spill is precautionary evidence of a likely fault, not proof of an offence — we test the rainfall, not the works' flow. Generated by River Hub.