Every overflow drains to a treatment works that serves a fixed area. When a works is too small for the flow it receives, spills follow. This crosses each works' estimated load against its permitted flow — and against the spill record — to say what the numbers point to.

Capacity across the River Dart

4 of the 12 works we track are estimated to take more flow than their permit allows — between them they serve about 2,462 people. A further 5 cannot be assessed at all, because we have not found a permit or a population estimate for them.

4
Over their permitted flow
estimated load above the permit
4
Have headroom but spill anyway
points upstream, not to capacity
5
Cannot be assessed
no permit or population on record
2,462
People on an over-loaded works
served by works over or at the limit
Works
Load against permit
Overflow at works
What that points to
WIDECOMBE_STW_WIDECOMBE IN THE MOOR
519 people · 16 m³/day permitted
454%
Over capacity
19 h
1 upstream · 16 pre-STW
Both
A capacity problem and upstream faults
SCORRITON_STW_SCORRITON
293 people · 25 m³/day permitted
164%
Over capacity
1,833 h
0 upstream
Treatment capacity
Needs investment or a lower permit
HARBERTON_STW_HARBERTON
1,357 people · 150 m³/day permitted
127%
Over capacity
1,829 h
0 upstream
Treatment capacity
Needs investment or a lower permit
HOLNE_STW_HOLNE
293 people · 36.4 m³/day permitted
113%
Over capacity
1,400 h
0 upstream
Treatment capacity
Needs investment or a lower permit
BROADHEMPSTON_STW_BROADHEMPSTON
500 people · 75 m³/day permitted
93%
Within capacity
1,039 h
0 upstream
No capacity signal
TOTNES STW
8,714 people · 3,967 m³/day permitted
31%
Within capacity
593 h
9 upstream · 976 pre-STW
Network faults upstream
Blockages, failed pumps or infiltration
PRINCETOWN STW
1,443 people · 1,023 m³/day permitted
20%
Within capacity
0 h
1 upstream · 16 pre-STW
Network faults upstream
Blockages, failed pumps or infiltration
BUCKFASTLEIGH STW
7,795 people · permit not found
Not known
Not assessed
2,187 h
5 upstream · 260 pre-STW
Network faults upstream
Blockages, failed pumps or infiltration
RATTERY_STW_RATTERY
580 people · permit not found
Not known
Not assessed
1,712 h
0 upstream
Not assessed
Permit or population missing
ASHPRINGTON_STW_ASHPRINGTON
population unknown · 181 m³/day permitted
Not known
Not assessed
25 h
0 upstream
Not assessed
Permit or population missing
DITTISHAM MAIN_STW_DITTISHAM
population unknown · 66 m³/day permitted
Not known
Not assessed
205 h
2 upstream · 533 pre-STW
Network faults upstream
Blockages, failed pumps or infiltration
STRETE_STW_DARTMOUTH
population unknown · 122 m³/day permitted
Not known
Not assessed
0 h
0 upstream
Not assessed
Permit or population missing

The black line marks 100% of permitted dry-weather flow; a dashed empty bar means no permit was found to measure against. Load is an estimate — population served × per-head water use, plus infiltration — not a permit-compliance finding. A works over 100% here is a signal to investigate, not a proven breach. Overflow hours are the works' own storm overflow in the last full year.

5 works we cannot assess

For BUCKFASTLEIGH STW, RATTERY, ASHPRINGTON, DITTISHAM MAIN, STRETE we have no permit or no population estimate on record, so we cannot check whether the works is big enough. This is a gap in the public record — not a clean bill of health — and it is the quickest thing on this page to fix: the permitted flow is public information a water company must supply on request.

Why this matters for reading spills

Works over capacity

If a works cannot treat the flow it receives, it spills to protect itself. The remedy is capital investment or a lower permitted load — years and millions, but it is the water company's to fix.

Headroom, but upstream spills anyway

A works with spare capacity whose network still spills points upstream — a blockage, a failed pump, or groundwater getting into the sewer. Often cheap to fix, and fixable now.

No permit found

Where we cannot find the permitted flow, the works cannot be assessed at all. That is a gap in the public record, and closing it is the first step to holding capacity to account.

How growth becomes spills

A developer has a section 106 right to connect to the public sewer, and the water company has a section 94 duty to accept the flow — but capacity is only funded on a five-yearly capital cycle. New connections can therefore arrive years before the works is enlarged to take them, and the overflow absorbs the gap. Schedule 3 to the Flood and Water Management Act 2010, which would make sustainable drainage mandatory and give a SuDS Approving Body a say, has been in force in Wales since 2018 but remains uncommenced in England — so here there is no such body.

What the permit actually sets

The permitted dry-weather flow is set by Formula A — roughly DWF + 1,360 × population + 2 × trade effluent (litres/day). The permit also sets a flow to full treatment, typically about three times DWF, below which everything must be treated rather than spilled. Our load figure compares estimated demand against that permitted DWF. 2 works in the catchment publish no permitted flow at all, so their load cannot be calculated — they show as not assessed, never 0%.